Giant turbines make the move to Catawba Nuclear Station

First step in preparing for Spring 2020 outage

This story first appeared on Duke Energy's storytelling website, illumination.

Catawba Nuclear Station in South Carolina took a big step in preparing for its refueling outage this spring.

The operative word being big.

Three low-pressure turbines, each weighing 184 tons, were transported by rail to Rock Hill then moved onto oversized trailers for a 13-mile trip to the Duke Energy-operated plant. The three trips took more than six hours each.

At the plant, the turbines were staged for their installation to ensure the plant can continue to deliver safe, reliable and carbon-free energy for customers. The company's Brunswick Nuclear Plant will also refuel one unit this year, while both the Oconee and McGuire Nuclear Stations will each have two outages in 2020. New turbines will continue to be installed at the Oconee plant. Nuclear plants shut down for refueling and maintenance every 18 to 24 months, in the spring and fall, when energy demand is lower. Workers replace about one-third of the used fuel assemblies with new ones.

2020-0113-catawba-turbine2-sized

Three new turbines for Duke Energy’s Catawba Nuclear Station make their journey from the Norfolk Southern railway line in Rock Hill, S.C., to the plant. The turbines and transport skids were unwelded from a railway car and secured on a special truck bed. The next day they were transported at 20 mph to the plant and hoisted inside.

2020-0113-catawba-turbine7-on-tracks-sized

Each General Electric turbine weighs 184 tons.

2020-0113-catawba-turbine53-on-the-way-sized

The turbine on its way to unit 1 at Catawba Nuclear Station.

2020-0113-catawba-turbine75-at-plant-sized
The turbine was moved to a spot on the turbine deck where it will stay until installation.
2020-0113-catawba-turbine104-lowered-sized

Nuclear power accounts for about half of all power generated by Duke Energy in the Carolinas.

2020-0113-turbine-oconee

A turbine awaiting installation at Oconee Nuclear Station in South Carolina.

 
 
 

Comments (3)

Posted October 24, 2022 by Hyukjin chung
Could you please let me know when and which units have been replaced the Low Pressure turbines by GE in Oconee and Catawba Nuclear Power plants?
Posted July 27, 2020 by Vincent Bischoff
Since the turbines are delicate and attached to the "transport frame" the best way to secure them to the rail car is to tack weld them.
Posted June 23, 2020 by Tim Marvin
These are a great set of pictures. But I don't understand what is meant by unwelding the transport skids from the railway car.

Leave a Reply

Please read our Comment Guidelines.

*
*
*

For real-time updates, follow us on Twitter

Follow Blog via Email

Enter your email address to follow this blog and receive notifications of new posts by email.

Opt out from these emails

Check out our new Facebook page